Definition
1. When, after the suspension of obligations by the requesting Party, the responding
Party takes measures to comply with the final panel report, the responding Party shall
notify the other Party and the CETA Joint Committee and request an end to the
suspension of obligations applied by the requesting Party.
2. If the Parties do not reach an agreement on the compatibility of the notified measure
with the provisions referred to in Article 29.2 within 60 days of the date of receipt of
the notification, the requesting Party shall request in writing the arbitration panel to
rule on the matter. Such request shall be notified simultaneously to the other Party
and to the CETA Joint Committee. The final panel report shall be notified to the
Parties and to the CETA Joint Committee within 90 days of the date of submission of
the request. If the arbitration panel rules that any measure taken to comply is in
conformity with the provisions referred to in Article 29.2, the suspension of
obligations shall be terminated.